Construction progress as of 12.11.2018

Construction progress as of 12.11.2018
12.11.2018
Construction progress as of 12.11.2018

Dear buyers, we would like to present You with the construction dynamics as of 12.11.2018.

The concrete slab is set above the 24th floor. The vertical structures of the 25th floor are reinforced.
The masonry of the basement, 2-4th, 9-16th floors is conducted.
The installation of the hidden wiring of power supply networks on typical residential floors in the monolithic structures is underway.
The installation of the internal networks for heating and ventilation, electricity supply, water supply, sewerage, low-current networks and smoke removal, "smart home" system, cement covering, wall plaster, and the finishing of common use areas  are held on the 5th floor.

You can see the photo report on the construction in our gallery.
Sincerely, Intergal-Bud.