Dear customers, we offer you the dynamics of construction on 04.03.19.:

Waterproofing device - 5-10 floor, basement.
Masonry - TE, 19, 21, 23, 27 floor.
The device of internal power supply networks - 5-11 floor.
The device of internal networks of heating and ventilation - 1-11 floor.
The device of internal water supply and sewage networks - 1-12 floor.
Device finishing works MOP - 28.25%
The device door structures and hatches - 4-24 floor.
Installation of elevator equipment - 40% (1-24 floor).
Roof installation - 16%
The device window designs - 5-16 floor.
The installation of metal fencing staircases - 6 floors.
The device of external engineering networks - 40%