Dear buyers, We bring to your attention the dynamics of construction as of 29.08.19:
The arrangement of the system "smart home" - 38% (layout of pipes on 7-22 floors).
Installation of ITP (individual heat points) - 85% (frame mounted).
Plastering of walls - 33% (ITP, commercial staircase, plinth, 3rd floor, entrance group, lobby)
Screed arrangement - 68% (plinth, 23-26 floor).
Hydro insulation arrangement in the travel zone - 60%
Laying - 4 floor and plinth.
Electrical works - 46% (5-24 floor).
Low-current systems - 41% (Works started on 5-24, 2-3 floors).
Ventilation and smoke removal - 16% (1-3 floor).
Plumbing - 72% (started: horizontal breeding under risers in the plinth; installation of distributor collectors).
Installation of finishing works MZK - 70% (putty of ceilings 6-18, tile 14-16 floor).
Arrangement of door structures - 69% (5-20 floor).
Installation of lift equipment - 80% (installation of cabins for freight and office lifts).
Roof arrangement - 60% (steam and hydro-barriers are arranged, an extruder is installed, a clay-concrete concreting screed, a screed of fine-grained concrete, a perimeter of the perimeter).
Arrangement of window structures - 5-22 floor.
Facade arrangement - 75% (metal-plastic balcony blocks are in operation, steam insulation is performed).
You can see a photo report on the construction in our gallery.
Sincerely, Intergal-Bud Company