Dear Buyers, we offer to your attention the dynamics of construction as of November 26, 18th:
Concrete slab of the technical floor, partially concrete concrete parapet. The installation of armored frame and formwork of vertical structures of a technical floor is carried out.
A laying is carried out - a socle, 1, 4, 14, 16, 17 floor.
The works on the installation of a hidden extension of power supply networks on typical residential floors in monolithic structures in a plate over 24 floors have been completed.
The arrangement of lightning protection is carried out only in a monolith.
The arrangement of the metal fence of staircase cages - 6th floor.
You can see the photo report on construction in our gallery.
Sincerely, the company "Intergal-Bud"