Dear buyers, we offer to your attention the dynamics of construction as of March 11, 19th:
Dear Buyers, we offer to your attention the dynamics of construction as of March 18, 19th:
Installation of waterproofing - 28% (5-10 floor, socle).
Laying - TP, 23, 24 floor.
The arrangement of internal power supply networks is 5-11 floors.
The arrangement of internal heating and ventilation networks is 1-11.
Installation of internal water supply and sewage networks - 1-16 floors.
Installation of finishing works MZK - 35%
Installation of door structures - 45% (4-25th floor)
Mounting of elevator equipment - 45% (1-24 floor).
Roofing - 16%
The arrangement of window constructions is 5-16 floors.
Facade installation - 26%
You can see the photo report on construction in our gallery.