Dear Buyers, we offer you the dynamics of construction as of September 10, 18th:
Reinforced and concrete vertical structures of the 20th floor. Concrete slab floor 19 floors. The installation of the formwork of the floor slab over 20 floors is started.
There is a laying - a socle, 2, 4, 6, 8, 9, 10, 11 floor.
Work is underway to install a hidden extension of low-voltage networks and power supply networks on typical residential floors in monolithic structures.
Plaster - 5th floor.
Decoration of the IGC - 5th floor.
You can see the photo report on construction in our gallery.
Sincerely, the company "Intergal-Bud"