Dear buyers, we bring to your attention construction dynamics as of 03.06.19.
Installation of the “smart home” system - 4% (layout of pipes on 7-21 floors.
Installation of individual heat plants - 60% (equipment installation is under way).
Wall plastering - 7% (individual heat plants)
Screeding - 29% (sole plate, 12th floor)
Hydro and thermal insulation in the passage area - 30%
Masonry - 3 floor and plinth.
Electrical works - 15% (5-21 floors).
Low-voltage systems - 11% (works started on 5-19, 2-3 floors).
Ventilation and smoke removal - 12% (1-11 floors; 4 smoke removals on the roof).
Plumbing works - 43% (works on installation of risers of water supply, sewerage, drainage sewerage on 1-24 floors are being performed, floor distribution of heating and water supply on the 20 and 21 floors is being performed).
Finishing works in common facilities - 52% (plastering of ceilings 6-10, 12-14, 23-24 floors).
Installation of door structures - 45% (4-24 floors).
Installation of elevator equipment - 75% (installation of cargo and office elevators).
Roofing - 55% (steam and hydro-barriers, extruder, keramzite concrete screed, screed made of fine-grained concrete, slag wool along the perimeter).
Installation of window structures - 5-16 floors.
Installation of facades - 44% (metal-plastic balcony blocks, vapor barrier).
You can see a photo report on the construction in our gallery.
Sincerely, Intergal-Bud Company