Dear buyers, we bring to your attention construction dynamics as of 02.05.19.
Hydro insulation in the passage area - 30%
Masonry - 3 floor and plinth.
Electrical works - 11% (5-18 floors).
Ventilation and smoke removal - 12% (1-11 floors).
Plumbing - 33% (1-24 floors).
Finishing works in common facilities - 47% (plastering of ceilings 6-10, 12-14 floors).
Installation of door constructions - 45% (4-24 floors).
Installation of lift equipment - 70% (1-24 floors).
Roofing - 50% (steam and hydro-barriers, extruder, keramzite concrete screed, screed made of fine-grained concrete, slag wool along the perimeter). Work on covering the vent shafts.
Installation of window structures - 5-16 floors.
Facade mounting - 26% (metal-plastic balcony blocks, steam insulation).
You can see a photo report on the construction in our gallery.
Sincerely, Intergal-Bud Company