Dynamics of construction as of 02.05.19

02/05/2019

Dear buyers, we bring to your attention construction dynamics as of 02.05.19.

Hydro insulation in the passage area - 30%

Masonry - 3 floor and plinth.

Electrical works - 11% (5-18 floors).

Ventilation and smoke removal - 12% (1-11 floors).

Plumbing - 33% (1-24 floors).

Finishing works in common facilities - 47% (plastering of ceilings 6-10, 12-14 floors).

Installation of door constructions - 45% (4-24 floors).

Installation of lift equipment - 70% (1-24 floors).

Roofing - 50% (steam and hydro-barriers, extruder, keramzite concrete screed, screed made of fine-grained concrete, slag wool along the perimeter). Work on covering the vent shafts.

Installation of window structures - 5-16 floors.

Facade mounting - 26% (metal-plastic balcony blocks, steam insulation).

 

You can see a photo report on the construction in our gallery.

Sincerely, Intergal-Bud Company

Other news

01/11/2021
Стартовали продажи пентхаусов

Стартуют продажи в комплексе бизнес-класса «Владимирский» от компании «Интергал-Буд».
Комплекс располож...

01/03/2021
Pantries for things - more space for people!
A cozy and comfortable apartment is when there is a lot of free space, an...
                            
Find out the price
Sales department
Address:
Kyiv
Pecherskyi district
street Staronavodnytska, 16b
Work schedule:
Mon-Fri: 09:00 - 19:00
Sat-Sun: 10:00 - 17:00
Recording for consultation:
(044) 392 45 18
E-mail:
info@intergal-bud.com.ua