Dear buyers, we bring to your attention construction dynamics as of 01.08.19.
The installation of the “smart home” system has begun - today the volume is estimated at 14%.
Installation of individual heat points is about to be completed - 85%.
Finishing works (walls plastering (Individual Heating Plants, commercial staircase, plinth) and screeding (19, 25, 26th floors and basement) are underway.
Hydro and thermal insulation in the passage area - 38%.
Masonry – the 4th floor and the basement.
Electrical works - 32% (5-24 floors).
Low-voltage systems - 27% (5-24, 2-3 floors).
Ventilation and smoke removal - 16% (1-3 floors).
Plumbing works - 64% (commenced: installation of distribution manifolds; heating radiators in common facilities; horizontal plumbing for risers in the plinth).
Ceiling plastering in common facilities - 6-10, 12-18 floors
Door assembly - 4-24 floors.
Installation of cargo and office elevator cars - 80%
Roofing works - 60%.
Installation of window structures - 5-22 floors.
Installation of facades - 69% (the balcony blocks and vapor barrier are underway).
You can see a photo report on the construction in our gallery.
Sincerely, Intergal-Bud Company