Dear buyers, We bring to your attention the dynamics of construction as of 25/09/19:
Facade (installation of granite 1-3 floor) - 30%
Wall plaster - 85%
Electrical work - 95%
Plumbing - 95%
Coupler arrangement - 90%
Arrangement of door structures - 80% (apartment and in MZK).
Insulation of walls by a minvat - 70%
Finishing works in MZK - 80% (puttying of ceilings, tiles).
Ventilation and smoke removal - 70%
Roof arrangement - 70% (work on the terraces).
Installation and commissioning of lifts - 80%
You can see a photo report on the construction in our gallery.